Program Timeline and Key Milestones
NYSERDA, with the support of the Program Manager, is responsible for developing the schedule of activities that will lead to the successful operation of the IEDR. You can find the current schedule of major milestones detailed in the table below. This page will continue to be updated as the program evolves.
IEDR Detailed Development Roadmap
Visit this page to learn more about upcoming releases of the IEDR and exciting new functionality, improvements to existing functionality, or technical fixes that will be available soon on the platform.
Previously in Phase 1, the IEDR Program relied on a series of program milestones as established by the Program Sponsor Implementation Plan (PSIP) to track program progress and initial use case development. The transition from Phase 1 to Phase 2 of program operations contained a shift in program progress tracking from monitoring a series of foundational program milestones to tracking IEDR platform and use case development activity.
Initial Phase 2 planning projections account for two Phase 2 program milestones. The Order Approving Integrated Energy Data Resource Phase 2 Budgets established one additional IEDR Program milestone, the “Phase 2 Status and Summary Report”, which is anticipated to be filed on or before April 1, 2026. The previous Phase 1 program milestone “Platform User Conference” was determined to be more suited as a Phase 2 program activity and is now being tracked accordingly.
Additional information on these two milestones and any potential emergent Phase 2 program milestones will be reflected here and in IEDR Program Quarterly Reports.
Phase 1 Program Milestones
Major Program Milestones | Program Topic | Date Expected | Status |
---|---|---|---|
IEDR Program Dashboard operational | Reporting | October 31, 2021 | Completed October 31, 2021 |
First quarterly report filed | Reporting | October 31, 2021 | Completed October 21, 2021 |
Program Charter to be adopted by the Advisory Group | Charter | Q4 2021 | Completed October 21, 2021 |
General Stakeholder Engagement Meeting (Virtual use case stakeholder event) | Stakeholder Engagement | Q4 2021 | Completed November 15, 2021 |
Stakeholder Engagement and Communication Plan drafted and finalized | Stakeholder Engagement | Q4 2021 | Completed October 29, 2021 |
Outreach to organizations that submitted use cases and may be aligned with prioritized use cases | Stakeholder Engagement | Q4 2021 (starting) | Started Q4 2021, as anticipated |
Use case interviews to assist in user story and user journey development | Stakeholder Engagement | Q4 2021–Q2 2022 | Started Q4 2021, as anticipated |
Workshops/focus groups for each use case to validate user stories and user journeys | Stakeholder Engagement | Q4 2021-Q2 2022 | Started Q4 2021, as anticipated |
Develop draft procurement documentation for IEDR Development team | Solution Architect + Development RFP | Q4 2021 | Completed December 31, 2021 |
IEDR Utility Data Assessment completed | Utility Coordination Group | Q4 2021 | Completed December 2021 |
Issue RFP for Solution Architect + Development contractor teaming arrangement and related services |
Solution Architect + Development RFP | Q1 2022 |
Completed March 25, 2022 |
Contract with Solution Architect + Development team executed, and work commences | Solution Architect + Development RFP | Q2 2022 | Delayed - Completed October 13, 2022 |
Sprint cycles focused on converting user stories/journeys for 3-5 use cases into functional IEDR prototypes | Public Iterations of IEDR | Q1 2023 | Delayed – Completed, originally anticipated Q4 2022 |
Final round of data access/security review and User Acceptance Testing of the IEDR’s first public iteration | Public Iterations of IEDR | Q1 2023 | Delayed – Completed, originally anticipated Q4 2022 |
First public iteration of the IEDR released | Public Iterations of IEDR | Q1 2023 | Delayed – Completed, originally anticipated Q4 2022 |
Sprint cycles focused on converting user stories/journeys for an additional 2-5 use cases into functional IEDR prototypes | Public Iterations of IEDR | Q1 2023 – Q4 2023 | Complete - Q4 2023 |
Phase 2 Proposal filed |
Reporting | May 12, 2023 |
Delayed - Completed (Originally anticipated January 15, 2023) |
Phase 1 Status and Summary Report filed | Reporting | April 30, 2024 | In progress - Delayed (Originally anticipated July 30, 2023) |
IEDR Platform User Conference | Stakeholder Engagement | Phase 2 |
Delayed to Phase 2 |
Steering Committee reviews and approves declaration of IEDR MVP | Public Iterations of IEDR | Q1 2024 | Complete – With deviation (Previously expected Q4 2023) |
IEDR MVP declared (5-10 use cases deployed) and end of Phase 1 | Public Iterations of IEDR | Q1 2024 | Complete – With deviation (Previously expected Q4 2023) |
Phase 2 Program Milestones
Major Program Milestones | Program Topic | Date Expected | Status |
---|---|---|---|
IEDR Platform User Conference | Stakeholder Engagement | TBA in Phase 2 | Not Started |
IEDR Phase 2 Status and Summary Report | Reporting | On or before April 1, 2026 | Not Started |
Go here to view the current list of use cases in development.